What are you looking for ?

Rs 50 million demanded for reconstruction of Dodhara Chandani suspension bridge

A A+ A-

MAHENDRANAGAR: A budget of Rs 50 million has been demanded for the Dodhara Chandani suspension bridge.

The suspension bridge over the Mahakali River was damaged by the flood occurred on September 30.

The people’s movement has been completely disrupted following the damages caused to one of the pillars of the bridge.

Planning chief of the Suspension Bridge Division, Shankar Budhathoki, informed RSS that Rs 50 million was demanded from the Ministry of Infrastructure Development in the first phase for the reconstruction of the historic suspension bridge that connects Bhimdatta Municipality with Dodhara Chandani.

“Detailed report for cost is awaited because soil needs testing for it. But there is still the water current in the soil/ground of damaged which hand hindered deploying technicians for soil testing,” planning chief Budhathoki said, adding that they would carry out other technical works and proceed with the contract process after the water current recedes in the river.

A two-member technical team led by deputy director general of the Suspension Bridge Division, Kamal Kumar Adhikari, reached Kanchanpur to study the damages. The team estimated that the bridge had suffered damage worth Rs 70 million, requiring the cost of Rs 200 million for reconstruction and resumption of service.

In addition to the collapsed pillar of the bridge, two others were also in fragile state, thereby requiring repair, according to the inspection team.

Meanwhile, Sudurpaschim Province government has allocated a budget of Rs 10 million for the reconstruction of the Dodhara Chandani suspension bridge. The bridge is also a well-known tourist destination in the country.